Review-first estimate

Creek Park Subdivision — source-linked breakdown

Every line item below points back to the drawing or spec it came from, declares a confidence band, and flags what still needs your review. Diffs show the correction an estimator made after sanity-checking the prediction. None of this numbers magic comes from us — it comes from the extraction trail, the reviewer, and the spec.

35 line items14 flagged for reviewDirect cost $2,033,971 · Total $2,501,785
BuildBid intentionally did not infer this

Bypass pumping during MH-12 replacement

Spec section 02 31 23 references a bypass plan but the mainline profile on C-301 does not show existing service to be kept in operation. Flow rates and duration are estimator judgement calls — BuildBid intentionally left this blank rather than guess.

Suggested scope to add manually: Add 1 LS bypass pumping (4" pumps + hose + fuel + monitoring) once estimator confirms active sewer tie-in staging.

Mainline Pipe· line 1

8" DIP Sanitary Sewer (0-6' depth)

1,420 LF · $62.00/LF · $88,040

High confidenceSource: C-3xx
Source referenceSheet C-3xxMainline Pipe — reference sheet

Measurement basis

1,420 LF extracted from mainline pipe callouts.

Needs estimator check because…

Routine spot-check recommended. No specific risk flagged.

Mainline Pipe· line 2

8" DIP Sanitary Sewer (6-8' depth)

1,380 LF · $72.00/LF · $99,360

High confidenceSource: C-3xx
Source referenceSheet C-3xxMainline Pipe — reference sheet

Measurement basis

1,380 LF extracted from mainline pipe callouts.

Needs estimator check because…

Routine spot-check recommended. No specific risk flagged.

Mainline Pipe· line 3

8" DIP Sanitary Sewer (8-10' depth)

848 LF · $85.00/LF · $72,080

Medium confidenceSource: C-3xx
Source referenceSheet C-3xxMainline Pipe — reference sheet

Measurement basis

848 LF extracted from mainline pipe callouts.

Needs estimator check because…

Review quantity against your own measurement before bidding.

Mainline Pipe· line 4

8" DIP Sanitary Sewer (10-12' depth)

300 LF · $98.00/LF · $29,400

Medium confidenceSource: C-301
Source referenceSheet C-301Sanitary Sewer Plan & Profile (STA 18+00 — 24+00)

Measurement basis

Aggregated from profile callouts on sheet C-301; depth band split inferred from invert elevations at MH-12 through MH-16.

Needs estimator check because…

Depth band 10-12' boundary depends on finished grade at STA 21+50, which is shown on civil C-102 but not cross-referenced on the profile. Verify before bidding deeper trench rate.

Mainline Pipe· line 5

8" PVC SDR-26 Sanitary Sewer (0-6' depth)

1,650 LF · $48.00/LF · $79,200

High confidenceSource: C-3xx
Source referenceSheet C-3xxMainline Pipe — reference sheet

Measurement basis

1,650 LF extracted from mainline pipe callouts.

Needs estimator check because…

Routine spot-check recommended. No specific risk flagged.

Mainline Pipe· line 6

8" PVC SDR-26 Sanitary Sewer (6-8' depth)

1,328 LF · $56.00/LF · $74,368

High confidenceSource: C-3xx
Source referenceSheet C-3xxMainline Pipe — reference sheet

Measurement basis

1,328 LF extracted from mainline pipe callouts.

Needs estimator check because…

Routine spot-check recommended. No specific risk flagged.

Mainline Pipe· line 7

8" PVC SDR-26 Sanitary Sewer (8-10' depth)

900 LF · $68.00/LF · $61,200

Medium confidenceSource: C-3xx
Source referenceSheet C-3xxMainline Pipe — reference sheet

Measurement basis

900 LF extracted from mainline pipe callouts.

Needs estimator check because…

Review quantity against your own measurement before bidding.

Laterals & Service· line 8

6" PVC SDR-26 Service Laterals

3,200 LF · $38.00/LF · $121,600

High confidenceSource: C-3xx
Source referenceSheet C-3xxLaterals & Service — reference sheet

Measurement basis

3,200 LF extracted from laterals & service callouts.

Needs estimator check because…

Routine spot-check recommended. No specific risk flagged.

Laterals & Service· line 9

4" PVC Cleanouts w/ Cast Iron Cover

80 EA · $285.00/EA · $22,800

High confidenceSource: C-3xx
Source referenceSheet C-3xxLaterals & Service — reference sheet

Measurement basis

80 EA extracted from laterals & service callouts.

Needs estimator check because…

Routine spot-check recommended. No specific risk flagged.

Laterals & Service· line 10

8"x6" PVC Tee Wye Fittings

71 EA · $165.00/EA · $11,715

High confidenceSource: C-3xx
Source referenceSheet C-3xxLaterals & Service — reference sheet

Measurement basis

71 EA extracted from laterals & service callouts.

Needs estimator check because…

Routine spot-check recommended. No specific risk flagged.

Laterals & Service· line 11

6" PVC 45° Bends

71 EA · $78.00/EA · $5,538

High confidenceSource: C-3xx
Source referenceSheet C-3xxLaterals & Service — reference sheet

Measurement basis

71 EA extracted from laterals & service callouts.

Needs estimator check because…

Routine spot-check recommended. No specific risk flagged.

Manholes· line 12

48" Precast Concrete Manhole (per VF)

478 VF · $310.00/VF · $148,180

High confidenceSource: C-301, C-302, C-303
Source referenceSheet C-301, C-302, C-303Sanitary Sewer Plan & Profile sheets

Measurement basis

Manhole VF = sum of (rim elev - invert elev) for 53 structures from profile sheets C-301 through C-303.

Needs estimator check because…

Profile sheets are clean and fully dimensioned. Spot-check 3 random structures against your own measurement.

Manholes· line 13

48" Precast Manhole Base Section

53 EA · $1850.00/EA · $98,050

High confidenceSource: C-3xx
Source referenceSheet C-3xxManholes — reference sheet

Measurement basis

53 EA extracted from manholes callouts.

Needs estimator check because…

Routine spot-check recommended. No specific risk flagged.

Manholes· line 14

Manhole Frame & Cover (traffic rated)

53 EA · $625.00/EA · $33,125

High confidenceSource: C-3xx
Source referenceSheet C-3xxManholes — reference sheet

Measurement basis

53 EA extracted from manholes callouts.

Needs estimator check because…

Routine spot-check recommended. No specific risk flagged.

Manholes· line 15

Manhole Drop Connection Assembly

8 EA · $2200.00/EA · $17,600

Low confidenceSource: C-401
Source referenceSheet C-401Sanitary Sewer Details & Structures

Measurement basis

Counted from drop-connection symbol in structure schedule on C-401. 8 symbols visible; legend confirms detail 3/C-402.

Needs estimator check because…

Two drop assemblies on the east branch may be standard connections — symbol is identical and only the profile call-out distinguishes them. Confirm with civil engineer.

Bedding & Backfill· line 16

ODOT #304 Pipe Bedding Material

3,940 TN · $28.50/TN · $112,290

High confidenceSource: C-3xx
Source referenceSheet C-3xxBedding & Backfill — reference sheet

Measurement basis

3,940 TN extracted from bedding & backfill callouts.

Needs estimator check because…

Routine spot-check recommended. No specific risk flagged.

Bedding & Backfill· line 17

Select Granular Backfill

5,200 TN · $18.00/TN · $93,600

Medium confidenceSource: C-401
Source referenceSheet C-401Typical Trench Section (Detail 2/C-401)

Measurement basis

Backfill volume computed from trench width (3.5'), depth bands, and total mainline LF. Convert to tons at 1.35 T/CY.

Needs estimator check because…

Select granular backfill requirement depends on soil report section 3.2 — current assumption is 100% import. If on-site material passes, backfill qty drops by ~40%.

Bedding & Backfill· line 18

Trench Compaction (95% Proctor)

7,826 LF · $4.50/LF · $35,217

High confidenceSource: C-3xx
Source referenceSheet C-3xxBedding & Backfill — reference sheet

Measurement basis

7,826 LF extracted from bedding & backfill callouts.

Needs estimator check because…

Routine spot-check recommended. No specific risk flagged.

Jack & Bore / Crossings· line 19

24" Steel Casing Jack & Bore

180 LF · $385.00/LF · $69,300

Medium confidenceSource: C-3xx
Source referenceSheet C-3xxJack & Bore / Crossings — reference sheet

Measurement basis

180 LF extracted from jack & bore / crossings callouts.

Needs estimator check because…

Review quantity against your own measurement before bidding.

Jack & Bore / Crossings· line 20

Bore Pit Excavation & Restoration

4 EA · $4500.00/EA · $18,000

Medium confidenceSource: C-3xx
Source referenceSheet C-3xxJack & Bore / Crossings — reference sheet

Measurement basis

4 EA extracted from jack & bore / crossings callouts.

Needs estimator check because…

Review quantity against your own measurement before bidding.

Outfall Sewer· line 21

8" PVC Outfall Sewer Main

4,852 LF · $54.00/LF · $262,008

Medium confidenceSource: C-3xx
Source referenceSheet C-3xxOutfall Sewer — reference sheet

Measurement basis

4,852 LF extracted from outfall sewer callouts.

Needs estimator check because…

Review quantity against your own measurement before bidding.

Outfall Sewer· line 22

Outfall Manholes (48" precast)

18 EA · $6800.00/EA · $122,400

Medium confidenceSource: C-3xx
Source referenceSheet C-3xxOutfall Sewer — reference sheet

Measurement basis

18 EA extracted from outfall sewer callouts.

Needs estimator check because…

Review quantity against your own measurement before bidding.

Outfall Sewer· line 23

Outfall Creek Crossing / Headwall

1 LS · $28500.00/LS · $28,500

Low confidenceSource: C-501
Source referenceSheet C-501Outfall Plan & Headwall Detail

Measurement basis

Lump-sum estimate from headwall detail 1/C-501 and creek section on C-502. Priced as single scope.

Needs estimator check because…

Creek crossing permit scope (USACE 404) is referenced on sheet G-001 general notes but not fully specified. Permit / mitigation costs may be owner-furnished or contractor-furnished — verify with specs division 02 41 13.

Site Work & Restoration· line 24

Erosion & Sediment Control

1 LS · $32000.00/LS · $32,000

Medium confidenceSource: C-3xx
Source referenceSheet C-3xxSite Work & Restoration — reference sheet

Measurement basis

1 LS extracted from site work & restoration callouts.

Needs estimator check because…

Review quantity against your own measurement before bidding.

Site Work & Restoration· line 25

Pavement Repair & Restoration

2,800 SF · $12.50/SF · $35,000

Medium confidenceSource: C-3xx
Source referenceSheet C-3xxSite Work & Restoration — reference sheet

Measurement basis

2,800 SF extracted from site work & restoration callouts.

Needs estimator check because…

Review quantity against your own measurement before bidding.

Site Work & Restoration· line 26

Seeding & Mulching Restoration

4.2 AC · $3800.00/AC · $15,960

High confidenceSource: C-3xx
Source referenceSheet C-3xxSite Work & Restoration — reference sheet

Measurement basis

4.2 AC extracted from site work & restoration callouts.

Needs estimator check because…

Routine spot-check recommended. No specific risk flagged.

Site Work & Restoration· line 27

Dewatering (Allowance)

1 LS · $45000.00/LS · $45,000

Low confidenceSource: G-003
Source referenceSheet G-003General Notes & Allowances

Measurement basis

Contractor-furnished dewatering allowance per general note 14, sheet G-003. No specific volume quantified.

Needs estimator check because…

Allowance may be under-sized for the 10-12' sections near the creek. Estimator judgement required — no plan data supports a specific number.

Site Work & Restoration· line 28

Traffic Control & MOT

1 LS · $18000.00/LS · $18,000

Medium confidenceSource: C-3xx
Source referenceSheet C-3xxSite Work & Restoration — reference sheet

Measurement basis

1 LS extracted from site work & restoration callouts.

Needs estimator check because…

Review quantity against your own measurement before bidding.

Testing & QC· line 29

Air Testing / Mandrel Testing

7,826 LF · $2.25/LF · $17,609

High confidenceSource: C-3xx
Source referenceSheet C-3xxTesting & QC — reference sheet

Measurement basis

7,826 LF extracted from testing & qc callouts.

Needs estimator check because…

Routine spot-check recommended. No specific risk flagged.

Testing & QC· line 30

CCTV Inspection

7,826 LF · $1.75/LF · $13,696

High confidenceSource: C-3xx
Source referenceSheet C-3xxTesting & QC — reference sheet

Measurement basis

7,826 LF extracted from testing & qc callouts.

Needs estimator check because…

Routine spot-check recommended. No specific risk flagged.

Testing & QC· line 31

Vacuum Testing (Manholes)

71 EA · $185.00/EA · $13,135

High confidenceSource: C-3xx
Source referenceSheet C-3xxTesting & QC — reference sheet

Measurement basis

71 EA extracted from testing & qc callouts.

Needs estimator check because…

Routine spot-check recommended. No specific risk flagged.

General Conditions· line 32

Mobilization / Demobilization

1 LS · $65000.00/LS · $65,000

High confidenceSource: C-3xx
Source referenceSheet C-3xxGeneral Conditions — reference sheet

Measurement basis

1 LS extracted from general conditions callouts.

Needs estimator check because…

Routine spot-check recommended. No specific risk flagged.

General Conditions· line 33

Construction Layout & Staking

1 LS · $22000.00/LS · $22,000

High confidenceSource: C-3xx
Source referenceSheet C-3xxGeneral Conditions — reference sheet

Measurement basis

1 LS extracted from general conditions callouts.

Needs estimator check because…

Routine spot-check recommended. No specific risk flagged.

General Conditions· line 34

As-Built Survey & Documentation

1 LS · $15000.00/LS · $15,000

High confidenceSource: C-3xx
Source referenceSheet C-3xxGeneral Conditions — reference sheet

Measurement basis

1 LS extracted from general conditions callouts.

Needs estimator check because…

Routine spot-check recommended. No specific risk flagged.

General Conditions· line 35

Bonds & Insurance

1 LS · $38000.00/LS · $38,000

High confidenceSource: C-3xx
Source referenceSheet C-3xxGeneral Conditions — reference sheet

Measurement basis

1 LS extracted from general conditions callouts.

Needs estimator check because…

Routine spot-check recommended. No specific risk flagged.